During the year, the Company has added transmission network of 7,350 Circuit Kms. 9 EHV AC sub-stations and transformation capacity of 13,700 MVA. The target and achievement of POWERGRID in project implementation during the year 2007-08 have been as under:
MOU Performance During FY 2008-09
| Sl. No. |
Project Implementation Parameter |
Target (Excellent) |
Achievement |
Percentage |
| 2008-09 |
2008-09 |
|
| I |
Activity for timely completion of transmission projects |
|
|
|
| 1 |
Foundation (Nos.) |
12000 |
12029 |
100.24% |
| 2 |
Tower Erection (Nos.) |
12000 |
12042 |
100.35% |
| 3 |
Stringing (Ckm.) |
7500 |
7207 |
96.09% |
| 4 |
Transformer Erection (Nos.) |
26 |
26 |
100.00% |
| 5 |
No. of Ckt. Kms. commissioned/ ready for commissioning |
5500 |
5556 |
101.02% |
| 6 |
Transformation Capacity addition (MVA) |
6285 |
6715 |
106.84% |
| 7 |
Inter Regional Capacity addition / Ready for commissioning (MW) |
3300 |
3800 |
115.15% |